'GEO Builders' were to complete a housing project by December 2024 and hand over the flats to the buyers. Due to excessive heat in the month of May and June 2024, the work slowed down and the project was getting delayed. The firm, in order to complete the project on time, hired more workers through a contractor and asked all the workers to work overtime. Due to the above measures taken by the management, the project was completed on time but the cost of building the flats increased by 10%.
Identify the correct option. 'GEO Builders' were: